Energy · Research report · 10 min read

Fusion's industrial path after the physics

Core thesis

Fusion commercialises as a supply-chain and licensing problem rather than a physics problem; the first plants will arrive where magnets, tritium, blankets, regulatory approval, and grid access are secured together, and net energy gain is necessary but not sufficient.

Why it matters

Private fusion funding hit a record 4.48 billion dollars in the year to July 2026, Commonwealth Fusion Systems expects net energy gain in 2027, and the first licences, power purchase agreements, and interconnection applications are being filed before the fuel and blanket technology exists to run a plant.

Focus areas

Superconducting magnetsTritium supplyFusion licensingState versus private

Executive summary

Fusion has crossed from a physics question to an industrial one. Private investors put a record 4.48 billion dollars into fusion companies in the year to July 2026, Commonwealth Fusion Systems says its SPARC demonstration is about 80 percent complete and expects net energy gain in 2027, and Helion has reportedly received the first licences to build a fusion power plant. Yet a plant that sells electricity needs more than a plasma that produces more energy than it consumes. It needs superconducting tape produced in volumes the industry has never delivered, tritium fuel from a global stock of roughly 25 to 30 kilograms that decays about 5 percent a year, breeding blankets that have not been demonstrated at full size, and a regulatory and grid-connection pathway that is still being written. ITER, the public benchmark, has slipped to 2039 for deuterium-tritium operation. This report argues that fusion commercialises as a supply-chain and licensing problem, and that the first plants will arrive where those gates are cleared together.

After the physics, the plant

Public attention to fusion follows physics milestones: ignition, record plasma temperatures, and the promise of net energy gain, the point at which a plasma releases more fusion energy than the heating that sustains it. These milestones matter, but they describe a laboratory result. A power plant must also convert heat to electricity, run for months with high availability, breed its own fuel, survive years of neutron bombardment, win a licence, connect to a grid, and sell power at a price a buyer will pay. Each requirement is a separate engineering and institutional problem, and several are less mature than the plasma physics.

The industry now behaves accordingly. Commonwealth Fusion Systems (CFS) has applied to the PJM grid operator for interconnection of a planned 400-megawatt plant in Virginia, signed offtake agreements with Google and Eni, and joined the UK's LIBRTI programme to test tritium blanket technology, all while its demonstration machine is still under construction (Utility Dive 2026). Helion is building a plant for Microsoft before its prototype has published a measure of net energy gain. Money, offtake, and permits are moving ahead of the technology that must justify them.

The useful frame is a chain with seven links: high-temperature superconducting tape, magnets, the machine, tritium, the blanket, the licence, and the grid connection and customer. Net energy gain tests one link. A plant is as strong as the least mature of the seven, and the weakest links are in materials and fuel, not in plasma physics.

    From ignition to industry

    For decades fusion was a public programme. ITER, the international tokamak under construction in France, is its benchmark, and its record shows how long industrialisation takes. Its 2024 baseline set the start of research operations in 2034, full magnetic energy in 2036, and deuterium-tritium operation in 2039, three to four years later than the 2016 reference, with an estimated 5 billion euros added to a budget already the largest in experimental science (Physics World 2024). By September 2026 six of nine vacuum vessel sector modules were in the tokamak pit, a three-year thermal shield repair had finished, and sector module 9, due in the pit in early December, was the critical path (ANS 2026).

    The private wave began in the 2010s on a different premise: that high-temperature superconducting magnets would let a tokamak be much smaller and therefore much cheaper and faster to build. The Fusion Industry Association's 2026 survey counts 56 companies, up from 23 in 2021, with 28 in the United States and four each in the United Kingdom, Germany, and China. Companies raised 4.48 billion dollars in the 12 months to July 2026, a record and 69 percent above the prior year, taking cumulative funding since 2021 to 14.24 billion dollars (FIA 2026). Five companies have raised more than 1 billion dollars, all American.

    The stated expectation is the 2030s: 71 percent of companies expect their first plant to deliver commercial electricity in that decade, and respondents estimate that a plant needs on average 2.7 billion dollars to become commercially viable (FIA 2026). The distance between that figure and the amounts raised shows that most of the industry is still funding the first plant, not a fleet.

      The private wave and what it bets on

      The leading programmes make different bets. CFS raised 1 billion dollars in a round announced on 30 July 2026, taking total funding to 4 billion dollars, with pension funds and sovereign wealth funds among the investors. Chief executive Bob Mumgaard said SPARC is about 80 percent complete and the company expects to show net energy gain in 2027, and that a string of ARC plants would need more than 1 billion dollars with 10 billion dollars the scale of capital needed to pursue fusion seriously (Utility Dive 2026). ARC, a 400-megawatt plant planned for Chesterfield County, Virginia, is targeted for the early 2030s, with Google contracting 200 megawatts and Eni more than 1 billion dollars of power.

      Helion pursues a pulsed approach intended to convert energy more directly. The company began construction of its Orion plant in Malaga, Washington in July 2025 under a power purchase agreement with Microsoft targeting 2028 delivery of at least 50 megawatts (S&P Global 2025), and reportedly became the first company to receive licences to build and operate a fusion power plant, from the Washington State Department of Health in June 2026 (Industrial Sage 2026). In the sources reviewed, Helion has not published a fusion gain figure for its prototype, so the 2028 date rests on schedule rather than on demonstrated performance.

        Exhibit 1Selected programmes, what each bets on, and the gating risk
        ProgrammeBet and gating risk
        ITER (public, France)A large low-temperature tokamak aimed at demonstrating burning plasma, with deuterium-tritium operation in 2039, so the risk is cost and schedule, not concept.
        CFS SPARC and ARC (private, US)Compact high-field tokamaks with net energy gain targeted for 2027 and a 400 MW plant in the early 2030s, so the risk is tape supply, tritium, and the blanket.
        Helion Polaris and Orion (private, US)A pulsed system with a 50 MW plant for Microsoft targeted for 2028, so the risk is that gain has not been published and the plant is committed first.
        BEST and CFEC (state, China)A state-led tokamak at Hefei scheduled for completion by the end of 2027 with a self-reported 5-fold gain target, so the risk is limited independent verification.

        Synthesised from FIA (2026), Utility Dive (2026), S&P Global (2025), ANS (2026), and Interesting Engineering (2025); programme targets are company or state claims and have not been independently verified.

        Magnets: tape as the first chokepoint

        The private tokamak thesis rests on one material. High-temperature superconducting magnets made from REBCO tape generate much stronger fields than their low-temperature predecessors, and because fusion power rises steeply with field strength, a machine can shrink dramatically. That moves the constraint from physics to manufacturing. A prototype compact device is estimated to need about 10,000 kilometres of tape, while the whole world's annual production capacity has been a few thousand kilometres (Commercial compact fusion 2025).

        The supply response is under way. A 2025 review counts roughly 15 high-temperature superconductor wire vendors with combined annual capacity above 5,000 kilometres of 12-millimetre-wide equivalent, with pulsed laser deposition producers making more than 3,000 kilometres a year and accounting for over half of global output (Commercial compact fusion 2025). Cost is the second gate. The Department of Energy's ARPA-E describes commercial tape at about 300 dollars per kiloampere-metre under fusion magnet conditions and says it must fall to roughly 10 dollars to be cost-competitive (ARPA-E n.d.). Sources put current prices between 100 and 300 dollars, and these figures are several years old.

        Fusion demand is now what justifies the factories. The risk is that every private tokamak depends on the same few tape suppliers, the same cryogenic and quench-protection engineering, and a supply base in which a small number of producers hold most of the capacity.

          Tritium: a fuel nobody makes

          Most near-term fusion designs burn deuterium and tritium, and tritium is almost nonexistent in nature. Civilian stocks are estimated at 25 to 30 kilograms and decline about 5 percent a year through radioactive decay. Canada is the largest civilian source, producing about 2 kilograms a year as a by-product of heavy-water reactor operation, and most of that output is earmarked for ITER over the next decade (FAS 2024). Starting a single commercial fusion reactor may require up to 10 kilograms, and operating a 1-gigawatt plant for a year may consume more than 55 kilograms.

          The arithmetic is severe. A stock of 25 to 30 kilograms is enough to start only a handful of commercial plants even if none of it were committed to ITER, and none of it can be stockpiled without losing about a twentieth a year. The only way to a fleet is for plants to breed their own fuel, which means a lithium blanket that produces more tritium than the plant burns. No full-size blanket has been demonstrated. An industry expert from the Electric Power Research Institute put the point bluntly: blanket technology is immature globally (Utility Dive 2026). The US government's marginal supply from Tennessee's Watts Bar reactors costs about 50,000 dollars per gram, against about 30,000 dollars for Canadian tritium, and is reserved for military use (FAS 2024).

          This makes tritium a chokepoint that does not yet appear in most investors' models. The FAS analysis argues that planned refurbishments of ageing Canadian reactors and ITER delays have kept open a window for several more years in which supply exceeds demand. After that window, plants that cannot breed fuel compete for a shrinking stock. Fusion's fuel logic is therefore the reverse of its marketing: the fuel is plentiful in principle, because lithium and deuterium are abundant, and scarce in practice, because the intermediate isotope is not made at scale.

            Licensing, grid, and state competition

            Regulation is moving faster than technology. In the United States the Nuclear Regulatory Commission proposed a rule in February 2026 that regulates fusion machines as a category of particle accelerator under the byproduct material framework of 10 CFR Part 30, consistent with Section 205 of the ADVANCE Act of 2024, rather than under the licensing regime for fission reactors, with a comment period that closed on 27 May 2026 (Federal Register 2026). The choice avoids reactor-style licensing and its costs. The United Kingdom follows a similar logic, with the Environment Agency and the Health and Safety Executive rather than the nuclear regulator overseeing fusion, a draft national planning policy statement for fusion in 2026, and a state-backed STEP prototype at West Burton with first operations expected around 2040 (DESNZ 2026).

            The grid is the less visible gate. CFS has submitted an interconnection application to PJM for ARC, which places a future fusion plant in the same queue as the generation and data-centre loads that have driven that market to its price cap (Utility Dive 2026). A plant that can generate for the grid still has to wait for the grid.

            State competition shapes the outcome. China Fusion Energy Co., a state-backed company under the China National Nuclear Corporation, was launched in 2025 with initial capital reported at about 1.6 billion dollars from state-owned enterprises (Caixin 2025), and its BEST tokamak at Hefei is scheduled for completion by the end of 2027 with a target of roughly five-fold energy gain, a claim that is self-reported and has had limited independent verification (Interesting Engineering 2025). The contrast with the American approach is one of structure: private capital moves quickly and concentrates risk in a few firms, while a state programme can commit to a long build without a quarterly funding test.

              The counter-case and three paths to the 2030s

              The strongest objection is that the industrial gates are engineering and will be passed as they were in other technologies. High-temperature tape has fallen in price and rising demand is expanding capacity. Blanket designs are in test programmes, regulators have chosen a lighter framework than fission, and capital is plentiful. Net energy gain in 2027 would be a decisive proof of the physics, and each successful step would draw in suppliers faster than caution predicts. This view is credible, and the rapid drop in the funding challenge, reported as the top short-term obstacle by 67 percent of companies this year against 84 percent last year, supports it (FIA 2026). What it cannot supply is a blanket and a fuel cycle that nobody has shown at scale, or the evidence that structural materials can withstand years of neutron bombardment while keeping a plant available for most of the year. A demonstration plant that runs for weeks is a different asset from one that sells power with the reliability a utility or data-centre buyer expects, and the gap between them is where earlier energy technologies have lost the most time and money.

              Three paths follow. In staged commercialisation, SPARC and Helion demonstrate their physics by 2027 to 2028, tape supply scales, and first plants in the early 2030s start on external tritium and add blanket demonstration plants, producing a few plants by the mid-2030s. In a fuel-constrained path, physics succeeds but tritium and blankets lag, so plants wait on supply and the industry consolidates around those with secured fuel. In a state-led path, a publicly funded programme, most plausibly China's, reaches an integrated plant first, and Western companies compete on cost and export. The signposts are observable: SPARC's published gain, a demonstrated breeding ratio, the NRC's final rule, ITER's sector welding, tape price and volume, and whether Orion delivers power in 2028.

                What determines who gets fusion first

                The record supports a selective conclusion. Fusion reaches the grid first where a developer secures the whole chain: tape at an acceptable price, a fuel cycle that does not depend on a fixed stock, a blanket tested in parallel with the machine, a regulator with a workable framework, and a buyer with a grid connection. It stalls where a company proves its physics and then waits for fuel, materials, or a queue position. A first plant is likely to be a demonstration with imported tritium. Fleets depend on breeding.

                For governments, the priority is the unglamorous infrastructure: tritium production and breeding test facilities, tape manufacturing, and regulatory certainty, rather than additional plasma experiments. For developers, the discipline is to treat fuel and blankets as the critical path and to secure offtake and interconnection on realistic dates. For investors, the safest exposure is in the enabling layers, tape, cryogenics, blanket materials, and tritium handling, which earn revenue whichever plant design prevails, while plant developers carry the binary risk.

                Fusion's physics has become a necessary condition and no longer a sufficient one. The first company to sell electricity will have solved a supply chain, not only a plasma.

                  References

                  1. 01Advanced Research Projects Agency–Energy. n.d. ‘Advanced HTS Conductors Customized for Fusion.’ Washington, DC: US Department of Energy.
                  2. 02American Nuclear Society. 2026. ‘ITER Reports “Substantial Progress” in Assembly and Installation Work.’ Nuclear Newswire, 9 September.
                  3. 03Caixin Global. 2025. ‘China Launches National Fusion Energy Firm With $1.6 Billion Investment From SOEs.’ 24 July.
                  4. 04Commercial Compact Fusion Triggered REBCO Tape Industry: Pulsed Laser Deposition Technology Opportunities and Challenges. 2025. ScienceDirect.
                  5. 05Department for Energy Security and Net Zero. 2026. Fusion Energy Strategy. London: UK Government, March.
                  6. 06Federal Register. 2026. ‘Regulatory Framework for Fusion Machines.’ 91 (38), 26 February. Washington, DC: US Nuclear Regulatory Commission.
                  7. 07Federation of American Scientists. 2024. ‘Fusion Energy Leadership Through Tritium Production Capacity.’ Washington, DC: FAS.
                  8. 08Fusion Industry Association. 2026. The Global Fusion Industry in 2026. Washington, DC: FIA.
                  9. 09Industrial Sage. 2026. ‘Helion Energy Becomes the First Fusion Company to Earn Regulatory Licenses to Build a Power Plant.’
                  10. 10Interesting Engineering. 2025. ‘China’s Fusion Reactor Aims for 5x Energy Gain by End of 2027.’
                  11. 11Physics World. 2024. ‘ITER Fusion Reactor Hit by Massive Decade-Long Delay and €5bn Price Hike.’
                  12. 12S&P Global. 2025. ‘Helion Energy Breaks Ground on Fusion Power Plant, Slated to Be Online in 2028.’ 30 July.
                  13. 13Utility Dive. 2026. ‘Commonwealth Fusion Systems Aims to Complete Demonstration Reactor with $1B Funding Round.’ 24 August.

                  Continue reading

                  Other research reports in the archive.

                  View all research

                  Energy

                  The making and unmaking of nuclear energy

                  A long-view study of how nuclear power rose through state ambition, weakened under financial and political strain, and returned as a strategic option in the age of decarbonization, energy security, and AI-driven electricity demand.

                  Read more

                  Technology

                  Superconductors: materials, technology, and impact on our world

                  An expert primer on superconducting materials, the engineering stack required to use them, and the sectors—from medical imaging to fusion magnets—where they are already reshaping what is physically possible.

                  Read more

                  Geopolitics

                  China's ambition beyond manufacturing and infrastructure dominance

                  A strategic analysis of how China is trying to move from scale-based dominance in factories and construction toward control over standards, advanced technology, capital formation, and geopolitical leverage—and the constraints now testing that ambition.

                  Read more

                  Energy

                  Power for compute: the grid as AI's binding constraint

                  A study of why artificial-intelligence computing is limited less by chips or aggregate energy than by the speed at which interconnection rules, grid equipment, firm generation, and tariffs can deliver power to specific sites, and of who is bypassing or coordinating those layers.

                  Read more

                  Geopolitics

                  Critical minerals: processing, not mining, is the chokepoint

                  An analysis of why leverage over critical minerals sits in refining, separation, and magnet-making rather than in the ground, how China has turned that position into a licensing regime, and whether price floors, stockpiles, and allied blocs can rebuild the missing middle of the chain.

                  Read more

                  Technology

                  Advanced semiconductors: why the stack, not the node, sets the pace of AI

                  An analysis of why frontier AI compute is limited by the weakest layer of a stack spanning lithography, leading-edge logic, high-bandwidth memory, and advanced packaging, and why export controls aimed at one layer are routed around through the others.

                  Read more

                  Technology

                  Southeast Asia's data-centre corridor: Johor, Singapore, and the cost of overflow

                  A study of how Singapore's rationing of data-centre capacity pushed compute into Johor, how power, water, and export-control compliance now constrain the corridor, and whether Malaysia can host the build-out on its own terms rather than as overflow for others.

                  Read more